|
Electric
Mountain





|
Construction
Construction of
the Main Caverns and Tunnels
The caverns, excavated deep from inside the hillside, house the main plant,
associated control equipment, switchrooms, workshops and personnel amenities.
Permanent cavern wall and roof rock support is similar throughout being
a combination of rock anchors (minimum length 8m), rock bolts (3.7m long)
and dowels together with mesh reinforced shotcrete to all exposed rock
faces. Local reinforcing, where necessary, was also carried out during
construction.
The caverns and
their major dimensions.
| Cavern |
Major dimensions
(metres) |
| |
Height |
Width |
Length |
| Machine
hall |
51.3 |
23.5 |
179.25 |
| Transformer
hall |
17.0 |
23.5 |
161.0 |
| Main
inlet valve gallery |
18.6 |
8.1 |
147.0 |
| Draft
tube valve gallery |
19.68 |
9.2 |
172.7 |
| Busbar
galleries 1/2, 3/4 and 5/6 |
18.4
|
14.8 |
5.19 |
| Starting
equipment house 1 |
26.25 |
14.2 |
36.0 |
| Starting
equipment house 2 |
33.8 |
14.2 |
28.0 |
Conventional reinforced
concrete and steel structures were used for the various floors and rooms.
However, computer studies needed to be carried out to evaluate stresses
and to check natural frequencies of the structures to ensure vibration-free
operation for the reinforced concrete structure supporting each pump-turbine/generator-motor.
All the tunnels are
similar in construction being supported throughout with rock bolts to
suit the particular rock structure and a layer of sprayed concrete, reinforced
in places with steel mesh, applied to most of the roofs and walls. They
are also similar in section having a flat invert (base) and semi-circular
roof. The largest is the plant access tunnel (8.0m wide by 7m high and
711m long) designed for transportation of the largest plant item, the
400/18kV generator-motor transformer. This tunnel also serves as the main
access tunnel for vehicles, personnel and plant to all areas of the cavern
complex. The heating and ventilating tunnels provide a link between the
main vertical ventilation shaft (chimney), which is 255m high by 5.0m
in diameter, and the small ventilation shafts serving the main caverns.
The tunnels alsoo provide access to part of the main cavern rock instrumentation
installation. The cable tunnel carries the twin 400 kV main station cables
between the main cavern area and the ground surface. Permanent and emergency
lighting facilities are provided in most of the tunnels.
|